Name of Project / Kind of Works:
132/33 kV Suli & Super steel substation Project - Stage 2
Total Value of the Contract:
695,000.00 USD
Duration:
8 months
Expected Commencement Date:
22/10/2020
Completion Date:
21/06/2021
Status of Project Completion:
100 %
Contracting Authority and Location:
Suli & Super steel Factories
Prime Contractor (P) or Subcontractor (S):
P
NPC Responsibility:
Design, Engineering Services, Delivery, Carrying out Site Erection Works, Testing, Commissioning and Energizing of Substation