Name of Project / Kind of Works:
132/33kV , 3x120MVA Mass Global Investment Steel plant substation
Total Value of the Contract:
237,479.00 USD
Duration:
6 months
Expected Commencement Date:
08/06/2013
Completion Date:
05/12/2013
Status of Project Completion:
100 %
Contracting Authority and Location:
ABB AB Substation, Vasteras, Sweden
Prime Contractor (P) or Subcontractor (S):
P
NPC Responsibility:
Supervision of site electrical works and carrying out site testing and commissioning of equipment for 132/33kV,3x120MVA substation provided for power supply of Mass Global Investment Steel Plant . Bazian -Sulaimaniyah