Name of Project / Kind of Works:
Stage 6 Substation Project , four new 33/11kV substations
Total Value of the Contract:
860,000.00 USD
Duration:
6 months
Expected Commencement Date:
15/07/2013
Completion Date:
15/01/2014
Status of Project Completion:
100 %
Contracting Authority and Location:
Plan Co.
Prime Contractor (P) or Subcontractor (S):
P
NPC Responsibility:
Carrying out the site electrical installation, connection works, site testing and commissioning for four new 33/11kV substation